First AP1000 reactor enters commercial operation

Date:2018-09-21 Source:President's Office and International Affairs Author:Bao Li

The full-power demonstration test run was completed at 3.57am on 21th, September, 2018. The reactor has now been "put into commercial operation conditions". 

In September 2007, the construction of four AP1000 units in China was permitted by the authorisation: two at Sanmen in Zhejiang province and two more at Haiyang in Shandong province. Construction of Sanmen 1 began in April 2009, while first concrete for Sanmen 2 was poured in December 2009. Construction of Haiyang 1 and 2 began in September 2009 and June 2010, respectively.

微信图片_20180702101842_meitu_8.jpg

Hot testing of Sanmen 1 - which simulated the temperatures and pressures that the reactor's systems would be subjected to during normal operation - was completed in June last year. The loading of fuel assemblies into its core began on 25 April. The unit achieved first criticality - a sustained chain reaction - on 21 June. On 27 June, nuclear-generated steam was used for the first time to successfully rotate the turbine at rated speed. Sanmen 1 was connected to the grid on 30 June, becoming the world's first AP1000 to achieve grid connection and power generation. It reached 100% power for the first time on 14 August.

Hot tests at Sanmen 2 were completed in January. That unit attained first criticality on 17 August and was grid connected a week later. The unit will now undergo gradual power ascension testing and is expected to enter commercial operation by the end of this year.

The successful construction of the Sanmen nuclear power project is an important achievement in the development of China's third-generation of nuclear power plants, and will vigorously promote the industrialisation of China's independent passive nuclear power technology.

Unit 1 of the Haiyang plant attained first criticality on 8 August and was grid connected on 17 August. Haiyang 2 is expected to start up in 2019.